Date submitted doesn't appear in demo data for ARV program

Description

During regression tests, I noticed that after authorization requisition for Lilongwe Health Center, Date submitted on the Approve Requisition screen doesn't appear.

Reproduction steps:

  1. Log in as administrator.

  2. Go to Requisition > Create/Authorize and select program ARV and facility Lilingwe Health Center.

  3. Click the "Proceed" button next to period with status "Submitted" Mar2017 01/03/2013-31-03-2017, and authorize.

  4. Go to Requisition > Approve and click the "View Requisition" button next to the previously authorized requisition.

  5. Date submitted for this requisition doesn't appear in the column.

Expected behavior:

  • For each submitted requisition, the date should be visible.

NOTE: This issue appears only in the demo data.

Environment

None

Assignee

Unassigned

Reporter

Joanna Szymańska

Epic Link

Components

Priority

Trivial
Configure