UAT Entry Criteria Checklist

 

ItemStatusOwner

Estimated Done Date

90% Confidence

Notes
  •  ThoughtWorks Development Complete
 Ron  
  •  ThoughtWork Demos Reviewed/Approved
 Timoteo  
  •  Tablet Solution Complete & Tested
    • procured
    • connectivity solution
    • lockdown
    • ui changes
    • tested
 Ron  
  •  Data Edit Feature (Access) Complete & Tested
 Ron3/8 
  •  VillageReach Analytical Report Workbook Complete & Tested
 Mike  Remove from UAT list?
  •  VillageReach Provincial (Portuguese) Workbook Complete & Tested
  • Monthly Summary Report, Map Report, Detail Reports
  • PDF of Monthly Summary Generated (one-off process OK)
  • HSG Feedback Incorporated
  • Calculations Tested
  • In Portuguese
 Mike  
  •  SELVdata ETL Complete
 Josh Dependent on TW Dev Complete (+5 days)
  •  vrMIS Data Migration Scripts Complete
 Josh  
  •  Architecture Document Complete
Status
colourGreen
Josh1/15 
  •  SELV Environment Installed. Procedure Tested & Documented.
 Josh  
  •  SELV Reference Data Files Uploaded & System Configured (in Portuguese)
 Josh  
  •  SELV Backup/Restore Process Tested & Documented
 Josh  
  •  UAT Plan Complete
Status
colourYellow
Sarah2/28In progress
  •  Training Materials Complete
Status
colourYellow
Sarah3/7Not started, but confident can be completed before training date
  •  Pre-Release Testing
Status
colourRed
Sarah Activity was not planned for. Need to do significant testing before release?