ThoughtWorks Changes for
...
v0.95 UAT Entry (Code Freeze)
Item | For Go Live |
---|
Remove target groups for all groups besides pregnant mothers from UI | Low Priority |
Facility Last Visit Date | Out of Scope. Will be done in SELVData. Josh Zamor will also handle last visit date update script after vrMIS data migration. |
Duplicate data entry issue Jira Legacy |
---|
server | JIRA (openlmis.atlassian.net) |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 448ba138-230b-3f91-a83e-16e7db1deed1 |
---|
key | SELV-12 |
---|
|
| waiting on feedback from Ron |
Cache Issue Jira Legacy |
---|
server | JIRA (openlmis.atlassian.net) |
---|
columns | key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution |
---|
serverId | 448ba138-230b-3f91-a83e-16e7db1deed1 |
---|
key | SELV-31 |
---|
|
| waiting on feedback from Ron |
Tablet column resizing | For 3/14 fix date |
Tablet numeric pop-up | TW to decide if this is feasible for 3/14 date by 3/5 |
Release Plan
Plan is for code freeze for initial project scope on 2/28 v.95
...
Josh to rebuild following week, and redo integration testing
UAT Entry Criteria Checklist
Item | Status | Owner | Estimated Done Date (90% Confidence) | Notes |
---|
- ThoughtWorks Development Complete (2/28 Scope)
| | Ron | 2/28 | |
- ThoughtWork Demos Reviewed/Approved
| | Timoteo | Done | Timoteo Chaluco (Unlicensed) validate showcase that will be posted tomorrow by 3PM EAT and send feedback to team |
- procured
- connectivity solution
- lockdown
- ui changes
- tested
| | Ron | 3/21 | Decide today what tablet to go with & connectivity Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week UI changes are outstanding for 3/14. |
- Data Edit Feature (Access) Complete & Unit Tested
| | Ron | 4/1 | Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans. |
- VillageReach Analytical Report Workbook Complete & Unit Tested
| | Mike | 2/28 | Remove from UAT list? |
- VillageReach Provincial (Portuguese) Workbook Complete & Unit Tested
- Monthly Summary Report, Map Report, Detail Reports
- PDF of Monthly Summary Generated (one-off process OK)
- HSG Feedback Incorporated
- Calculations Tested
- In Portuguese
| | Mike | 2/28 | |
- SELVdata ETL Complete & Unit Tested
| | Josh | Josh | Outstanding Issue: Last Visit Date is only outstanding item |
- vrMIS Data Migration Scripts Complete & Unit Tested
| | Josh | 2/27 | |
- Architecture Document Complete
| | Josh | 1/15 | |
- SELV Environment Installed. Procedure Tested & Documented. SSL Cert.
| | Josh | Josh | Josh needs to talk to Mike then can provide date later today. |
- SELV Reference Data Files Uploaded & System Configured (in Portuguese)
| | Josh | 2/28 | |
| | Sarah | 2/28 | In progress |
- Training Materials Complete (Tablets, Reports, UI)
| | Sarah | 3/7 | Not started, but confident can be completed before training date |
- Integration End-to-End Tests (SELV-> SELVData -> Reporting)
| | Sarah, Vidya, Josh, Timoteo | 3/7 | New. |
| | Josh | JOSH to provide | New |
| | | | |
...