ItemStatusOwner

Estimated Done Date

(90% Confidence)

Notes
  •  ThoughtWorks Development Complete (2/28 Scope)
Status
colourYellow
Ron2/28 
  •  ThoughtWork Demos Reviewed/Approved
Status
colourYellow
TimoteoDone

Timoteo Chaluco (Unlicensed) validate showcase that will be posted tomorrow by 3PM EAT and send feedback to team

  •  Tablet Solution Complete
    • procured
    • connectivity solution
    • lockdown
    • ui changes
    • tested
Status
colourRed
Ron3/21

Decide today what tablet to go with & connectivity

Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week

UI changes are outstanding for 3/14, then need to be rolled into build (3/21)

 

  •  Data Edit Feature (Access) Complete & Unit Tested
Status
colourRed
Ron4/1Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans.
  •  VillageReach Analytical Report Workbook Complete & Unit Tested
Status
colourYellow
Mike2/28 
  •  VillageReach Provincial (Portuguese) Workbook Complete & Unit Tested
  • Monthly Summary Report, Map Report, Detail Reports
  • PDF of Monthly Summary Generated (one-off process OK)
  • HSG Feedback Incorporated
  • Calculations Tested
  • In Portuguese
Status
colourYellow
Mike2/28 
  •  SELVdata ETL Complete & Unit Tested
Status
colourYellow
JoshJoshAlmost complete. Last Visit Date is only outstanding item
  •  vrMIS Data Migration Scripts Complete & Unit Tested
Status
colourGreen
Josh2/27 
  •  Architecture Document Complete
Status
colourGreen
Josh1/15 
  •  SELV Environment Installed. Procedure Tested & Documented. SSL Cert.
Status
colourYellow
JoshJoshJosh needs to talk to Mike then can provide date later todaytalked with Mike and now has access to the service issuing the certificate.  Waiting for their verification process to complete.  No time estimate currently.
  •  SELV Reference Data Files Uploaded & System Configured (in Portuguese)
Status
colourYellow
Josh2/28 
  •  UAT Plan Complete
Status
colourYellow
Sarah2/28In progress
  •  Training Materials Complete (Tablets, Reports, UI)
Status
colourYellow
Sarah3/7Not started, but confident can be completed before training date
  •  Integration End-to-End Tests (SELV-> SELVData -> Reporting)
Status
colourYellow
Sarah, Vidya, Josh, Timoteo3/7New.
  •  Data Completeness Report
Status
colourRed
JoshJOSH to provideNew