1. Project

...

  • Configuration of Zambezia and Tete provinces
  • Addition of Rotavirus, IPV, and MSD vaccines
  • Usability improvements

2. Scope

The scope of the SELV Updates project includes new configuration for several of the changes, to be completed in advance of the release, as well as new features deployed with the new release in January.

...

 
Risk
Description

Risk Level

(High, Medium, Low)

Comments
 On-site supportNo onsite training, knowledge transfer, or technical support in Mozambique due to lack of travel budget  MediumAll knowledge transfer and support remote - with minor changes is feasible but risk prolonging issues and miscommunication without on-site support
 Release/deployment dateIdentification of an appropriate date to close access to production for update Medium     
Initiation of Feb. distributionsThe deployment at the beginning of February will likely overlap with some of the distributions in Feb. For the deployment, users will be locked out of the production system and Feb. distributions cannot be initiated ahead of timeMediumAll Feb. distributions that overlap with the deployment should be done on paper. If any Feb. distribution is initiated before the deployment it will be deleted prior to the deployment.

5. UAT Plan

Task
Start
End
Responsible
Status
Comments

Pre-UAT testing

12/28/151/8/16Christine

1st round complete

 

Changes deployed to UAT

 1/8/16

1/

14

15/16

Ben

 

 

Functional testing

1/14/161/1522/16Christine

 

 

UAT Testing

1/15/16

1/2225/16

Tatenda

 

 

Report Testing

1/15/16

12/225/16

Christine

 

 

Bug fixes

1/22/16

1/2829/16

Ben/SolDevelo

 

If any bugs in SolDevelo's work are identified at this point, they will be asked to correct them

Code Freeze1/2829/16 Rich  
Training materials complete1/29/16  Christine/Tatenda  

6. Deployment Plan

Activity
Responsible
Timeline
Comments
User AcceptanceTatendaJan. 22nd25nd 
Code FreezeRichJan. 29th 
January Data Entry CompleteTatendaJanFeb. 25th5th 
SELV Production locked to end usersRich/BenJanFeb. 29th8th 
Full System Back-upBenFeb. 1st8th 
Bring down production systemBenFeb. 1st 8th 
Install new versionBenFeb. 1st 8th 
Run Upgrade ScriptsBenFeb. 1st 8th 
Configuration updatesChristineFeb. 1st 8th 
Validation TestingChristine/TatendaFeb. 1st 8th 
Status Meeting - Go / No-GoChristineFeb. 1st 8th 
TrainingTatendaJan. 25th - Feb. 8thMainly targeted for ColdTrace provinces
SupportChristineFeb. 1st 8th - March 1st