DateActivityResponsible
5/23
  •  Code Freeze
Ron
 
  •  Data Entry Freeze for vrMIS
Tatenda
 
  •  Final code deployment to SELV
Josh
5/26
  •  Seattle Holiday
n/a
 
  •  Deadline for configuration data: Users, Facilities
Tatenda
5/27
  •  SELV Configuration Updates
Sarah
5/28
  •  SELV Testing:
  • smoke test
  • regression for new features
  • exploratory testing
  • configuration check
Sarah
5/29
  •  Vidya to MOZ
Vidya
 
  •  Reset selv-training database to remove Argentina data
Josh
5/30
  •  Deadline for Refrigerator Inventory
Tatenda
 
  •  Final training materials to Maputo office for printing
Rachel
6/2
  •  Training Materials Printed, Laminated, Bound
Tatenda
 
  •  Load Refrigerator Data
Tatenda/Vidya
6/3-6/4
  •  Training
Tatenda

...