- Showcase 3 new features - UI and Requisition
- (1) Offline requisition form - form fill-out, not initiation or approval
- (2) Emergency requisitions - working in UI
- (3) My Supervised Facilities requisitions - working in UI
- Order Service - API
- Split orders into an independent service (1314)
- Goal: After this sprint, a team is ready to work in parallel on significant orders features (to discuss at Monday Sprint 13 Q&A meeting)
- Bugs
- 13 bugs from list below
- Extension Modules
- publishing to Maven and being able to deploy an extended service
- stretch goal is starting the extending data tooling (Team ILL)
Remember, we aren't requiring that all 4 of these go into sprint 13 — please only pull in as much work as we can finish in this sprint, but please pull items into the sprint in this priority order.
1. Showcase 3 new features - UI and Requisition
...