blahFeb 1 2017 - Feb 15 2017
Themes
See Backlog Grooming Sprint 19
Process Improvements
Retrospectives from the past sprint below inform what we want to improve during this sprint.
Team ILL:
- Prioritize: Focus on priorities for what has to be in 3.0 release. We will mark critical and blockers again to help our focus.
- Contact Tests: Paweł Gesek, Josh will reach out about the Contract Tests to talk about fixing any remaining buggy issues there.
- Stress Testing: Brandon will schedule a stress testing session so we can make sure performance is good.
- Bonus: We are going to eat donuts and plan some social activity to celebrate when 3.0 is released.
Teams AYIC/TOP: /wiki/spaces/OP/pages/111099581
Velocity
It was another record-breaking sprint! We accomplished 257.5 story points, 37 by Team ILL and 220.5 by Teams AYIC/ToP. This is the best velocity during the whole OpenLMIS 3 project. See Burn-up for 3.0 Release for details.
Showcase
Video: OpenLMIS End of Sprint Showcase-20170215 1504-1.arf
The following 87 tickets were completed this sprint and covered at the showcase: