  • Team will need to determine if there is a need for Sarah to return to Mozambique for training and roll-out after Josh’s visit.

Timeline

  •  May 5-9: Technical assessment trip

...

  •  Friday May 9th:  Trip debrief. Assess readiness to launch in June. Identify gaps. Identify resource requirements for launch.

...

  •  June 1: SELV live, ready for production data entry

...

  •  Week of June 2-6: Maputo & Gaza Training

...

  •  Week of June

...

  • 16th: Cabo Delgado & Niassa Training
  • SELV Training for Field Coordinators
  • Tableau Reports Training for all PAV Staff
  • Data Entry of May distribution visit forms in SELV. All April data is entered in vrMIS. All May data is entered in SELV.

...