Schedule
3/3 | 3/12 | 3/13 | 3/19 | 3/2124 | 3/2428 | 3/31 | 4/267 | 4/214 | |
---|---|---|---|---|---|---|---|---|---|
Pre-UAT Testing | seattle | ||||||||
UAT Release | * | ||||||||
Website Testing / Maputo Data entry | seattle/maputo | ||||||||
Report Testing | seattle/maputo | ||||||||
Bug Fixes | seattle | ||||||||
Production Code Release/Freeze | * | ||||||||
Integration | seattle | ||||||||
Final UAT on Production Release Candidate | maputo | ||||||||
Go Live/ Start Training |
UAT Testing Approach
...