Comment: added implementation release recommendations

...

  • Release Notes are updated to state that this is the official release and include the date of the release
  • Reference Distribution is released! It contains the same components as the accepted Release Candidate and has its official version (e.g. openlmis-ref-distro v.3.7.0)
  • Share Release with the OpenLMIS community along with the final Release Notes

After publishing the release, Active Development can resume.

Implementation Release Process

Below is the recommended process that OpenLMIS implementations use Implementations are typically composed of multiple core OpenLMIS components plus some custom components or extensions, translations and integrations. It is recommended that OpenLMIS implementations follow a similar process as above to receive, review and adopt verify updates of OpenLMIS v3.

Key differences for implementation releases:

  • Upstream Components: Implementations treat the OpenLMIS core product as an "upstream" vendor distribution. When a new core Release Candidate or Release are available, they are encouraged to pull the new upstream OpenLMIS components into the implementations CI/CD pipeline and conduct testing and review.
  • Independent Review: It is critical for the implementation to conduct its own Review Period. It may be a process similar to the diagram above, with multiple Release Candidates for that implementation and with rounds of manual regression testing to ensure that all the components (core + custom) work together correctly.
  • Conduct Testing/UAT on Staging: Implementations should apply Release Candidates and Releases onto testing/staging environments before production environments. There may be a full manual regression test cycle or a shorter smoke test as part of applying a new version onto the production environment. There should also be a full set of automated tests and performance tests, similar to the core release process above, but with production data in place to verify performance with the full data set. The testing/staging environment should have a recent copy of production data and should have an identical environment.
  • Follow Best Practices: When working with a production environment, follow all best practices: schedule a downtime/maintenance window before making any changes; take a full backup of code, configuration and data at the start of the deployment process; test the new version before re-opening it to production traffic; always have a roll-back plan if issues arise in production that were not caught in previous testing.