Agenda

  • Level Setting: Goal of delivery
    • Project Period: 15 Jan 2018 - (In negotiation depending on spend)
    • Interim goals:

      1. We want a flashy OpenSRP to OpenLMIS proof of concept by March 26th 2018
        1. What we build needs to lend itself to post demo activities
        2. We will need to maintain an active list of technical debt as we get to the March demo
      2. The long term goal is to ensure the full SOW is delivered
        1. It will have a more robust integration (eg, addressing the product model, facility list)


  • Goal of the proof of concept is to show integration:
    • Requesting stock
      • We need to work around the feature flow for the demo
      • Key: If you collect information on the mobile device, this is a way to save time in the requisition process.
    • Notification from OpenLMIS to OpenSRP
      • In the mobile app, I'm told what shipments are coming
        • I shipped stock in OpenLMIS, then I go to OpenSRP to show that it's on the way
  • Implications on meeting structure:
    • What needs to be delivered for the demo vs what are the long term investments
  • The first iteration is about the GAVI demo that's scheduled the week of 26 Mar 2018
    • What are the visual items we need to demo?
      • Track ins and outs, record wastage, set VVM status, lots with expiration dates
      • Stretch: Request stock from the mobile application to OpenLMIS ← Needs better definition
  • Review high level document OpenSRP and OpenLMIS Integration and discuss shared understanding
  • Talk about scope of the demo:
    • If you 
  • Discuss project management approach
    • Wiki spaces
    • Team members (Ephraim Muhia, Sam Githengi)
    • Sprint Schedule:
      • Line up with Other Sprints - First Sprint Date?
  • Craig will walk the team through design approach (Technical document OpenSRP and OpenLMIS High Level Design Spec)
    • Review and take notes on discussion points in the document

...