Goals

  1. Roll-overs: finish tickets rolled over from Sprint 9 (32 tickets)
  2. Requisition Service: push to finish OLMIS-760 and OLMIS-741 (details will be discussed at a 'Planning 3.0 Beta' meeting Thursday 4pm Poland / 7am Seattle)
  3. Requisition UI: get Nick and SolDevelo UI staff to collaborate to get a visible UI in place (also will be discussed at the same meeting)

Note: We are not adding more tickets from the Backlog into Sprint 10 at this time. The large volume of tickets rolling over may be enough to keep the teams busy for most of the sprint. If the roll-over tickets are all completed we can add more from the Backlog later during the sprint. Keep in mind that many of the tickets rolling over have already rolled over for a few sprints. Before we add more to the sprint or pull from the backlog, we have to complete these.

Process Improvements

  1. Slack End-of-Day Check-Ins: All SolDevelo and VillageReach team members are asked to post a two-sentence message in Slack #general at the end of their work day. The message should answer two questions: (1) What did I work on today? (2) What is blocked or does someone else need to know about?
  2. Tech Meetings on Skype/screensharing: Nick and Chongsun will schedule with Sebastian, Chris, and maybe Paweł or others if appropriate.
  3. Continue the other process improvements that have been made recently, including:
    1. developers checking in code daily to 'master' branch;
    2. VillageReach and SolDevelo working together to improve the object-oriented design (sequence diagrams, class diagrams);
    3. estimating tickets during sprint planning so we can measure velocity and plan sprint work-loads more accurately.

Showcase

Video: OpenLMIS End of Sprint Showcase-20161012 1405-1.arf

...