ThoughtWorks Changes for v0.95 UAT Entry (Code Freeze)
Ron Pankiewicz determine approach to duplicate data entry issue and which release a fix (if necessary) can be included in. Due 2/28.Item | For Go Live | version |
---|---|---|
Remove target groups for all groups besides pregnant mothers from UI | Low Priority | v1 |
Facility Last Visit Date | Out of Scope. Will be done in SELVData. Josh Zamor will also handle last visit date update script after vrMIS data migration. | n/a |
Duplicate data entry issue - SELV-12Getting issue details... STATUS | tbd |
|
Cache Issue - SELV-31Getting issue details... STATUS | Ron Pankiewicz (Deactivated) determine approach for cache issue and which release a fix (if necessary) can be included in. Due 2/28. | tbd |
Tablet column resizing | For 3/14 fix date | v1 |
Tablet numeric pop-up | TW to decide if this is feasible for 3/14 date by 3/5 | tbd |
Release Plan
Plan is for code freeze for initial project scope on 2/28 v.95
Bug fix release 3/14 v1.0
Josh to rebuild following week, and repeat integration testing by
UAT Entry Criteria Checklist
Item | Status | Owner | Estimated Done Date (90% Confidence) | Notes |
---|---|---|---|---|
| YELLOW | Ron | 2/28 | |
| YELLOW | Timoteo | Done | Timoteo Chaluco (Unlicensed) validate showcase that will be posted tomorrow by 3PM EAT and send feedback to team |
| RED | Ron | 3/21 | Decide today what tablet to go with & connectivity Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week UI changes are outstanding for 3/14.
|
| RED | Ron | 4/1 | Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans. |
| YELLOW | Mike | 2/28 | Remove from UAT list? |
| YELLOW | Mike | 2/28 | |
| YELLOW | Josh | Josh | Outstanding Issue: Last Visit Date is only outstanding item |
| GREEN | Josh | 2/27 | |
| GREEN | Josh | 1/15 | |
| YELLOW | Josh | Josh | Josh needs to talk to Mike then can provide date later today. |
| YELLOW | Josh | 2/28 | |
| YELLOW | Sarah | 2/28 | In progress |
| YELLOW | Sarah | 3/7 | Not started, but confident can be completed before training date |
| YELLOW | Sarah, Vidya, Josh, Timoteo | 3/7 | New. |
| RED | Josh | JOSH to provide | New |
Production Readiness Checklist
Back-Up/Resore process tested and documented