Schedule of Key Activities
Date | Activity | Responsible |
---|---|---|
5/23 |
| Ron |
| Josh | |
5/26 |
| n/a |
| Tatenda | |
5/27 |
| Josh |
5/28 |
| Sarah |
| tatenda | |
5/29 |
| Vidya |
| Josh | |
5/30 |
| Tatenda |
| Rachel | |
6/1 |
| Tatenda |
| Tatenda/Vidya | |
6/2-6/3 |
| Tatenda |
Roles & Responsibilities Status Report
Activity | Responsible | Due | Status | Issues/Blockers |
Overall Project Management | Sarah | n/a | YELLOW | Sarah to send status email on tasks. SELV-286 |
Scheduling Field Training | Aida | 5/19 | YELLOW | Need dates for Niassa and Cabo Delgado. Vidya to follow-up with Aida. |
Delivering Field Training | Tatenda | 6/2- 6/20 | GREEN | |
Process Knowledge Transfer | Vidya | Ongoing | GREEN | |
Refrigerator Inventory | Tatenda | 5/30 | RED | Will not be done for all provinces in time for configuration. Backup plan is to pre-enter what is on provincial inventory then update (delete old entry, add new entry) once inventory is in. |
Software Development (Code Freeze) | Ron | 5/23 | GREEN | On schedule. Ron to alert Josh when code is done. |
Tablet Field Trial | Tatenda | 6/3 | GREEN | Tablet field trial will start for July distribution. All three tablets are good to go. Tatenda to get movitel modems and adaptors and stabilizers. |
Training Materials | Vidya | 6/1 | YELLOW | Timeline is tight. Back from translator 5/30, must be to Maputo in final A4 format on 5/31. Maputo team to print/bind/laminate by 6/1.
|
vrMIS Data Migration | Josh/Vidya | 5/23 | RED | March data is currently incomplete in vrMIS. Proposed plan is to migrate all vrMIS data from Feb-14 and earlier, then have Argentina do March and April data entry, with field coordinators doing May during training. Vidya checking with Tatenda on data completeness status and cause. |
Final Deployment to SELV and SELV-Training | Josh | 5/26 | YELLOW | Argentina data will remain on SELV training until next thursday.
|
Final System Configuration (Refrigerators, Products, Cachement Population, Users, Facilities) | Sarah | 5/28 | YELLOW | Rachel to update cachement populations upload file SELV-98 Rachel to see if she can identify added/removed facilities SELV-241
|
Final Testing | Sarah | 5/30 | GREEN | Smoke Test Regression on changed features Validate configuratipon Poking around on SELV training |
Reporting Distribution Process | Vidya (with planned transfer to Tatenda) | 6/15 | GREEN | Vidya to update SOP with location where files will be stored SELV-223 Vidya and Tatenda to confirm reports meet user needs during training SELV-263 |
Notes
vrMIS data will be entered through March 2014
March Data Incomplete: Niassa and Gaza.
April data for Maputo already entered in vrMIS.
Reports can't run until all data is in a consistent state for all provinces.
Reports for training: Workbooks through February. Vidya to save final workbooks. Vidya and Josh to work together on this.
Argentina to help with data entry catch-up as needed.