Priorities

For Sprint 22, our target is to release ref-distro version 3.0.1 by the end of this sprint (sprint ends March 29). This means bugs, performance issues, security issues, adding test coverage, and refactoring. However, we have started to add some additional features. Please make sure component leads are aware and releasing their component as 3.0.1 OR 3.1.0 OR 4.0.0 when necessary. Please take care on breaking API compatibility or functionality! Components can put their release out any time (don't need to wait until the very last day of the sprint). Josh Zamor will be helping us establish a process where each component can put out a 3.0.1 release and then switch to working towards 3.1.0-SNAPSHOT.

Goals for ref-distro 3.0.1:

Warning!

We need to release during this sprint, so we do not want to start work that might be half-done at the end of the sprint. We cannot leave half-broken things in for the release. Please work in the priority order below, because we've carefully prioritized what is more important for the 3.0.1 release.


Questions:

Breaking changes after auth-reference data dependency switch - endpoints have changed:

We could get around this by:



Bugs (mostly UI)

UI Features

Administration Screens (needed for ref-distro 3.0.1)

FYI: We will address User Roles and Facilities admin screens in later sprints.

Priorities (in order):

Stretch goals/nice to do—only pick these up after the other MUST sections below are done:


Requisition Features


Fulfillment Features 

Platform Features


To Be Discussed during Q&A Meeting

Team ILL

Reporting Epic OLMIS-2048 contains: 

Holding Off

Parking Lot

Spike Program Data - need tickets to be made and clearly state what the outcome of the spike should be

Performance (sprint 22)