Objective: to continue addressing critical bugs (performance and major UI issues)
Reference UI
NR: These will make working with the UI easier
Stretch:
- - NR: Angular strap has hard coded string, might need another library
Requisition
Working on 3.1.5-SNAPSHOT
- Brandon Bowersox-Johnson to create a ticket to ...
- (In addition to what Łukasz included in his daily report on timeouts - we have increased the maximum execution time, but this is a temporary workaround. The requests already take too long time for certain things (especially reports since they usually require a lot of data). The root reason is requisition related endpoints returning a lot of unnecessary data - I've created a ticket for this in core (OLMIS-2533) but if it becomes problematic quickly we may need to fix it ourselves and contribute this to the core product - Sebastian 5/17)
- Remove previous requisition history
- Do BA work to decide what is actually needed (where/when)
- FYI, the Malawi logged bugs ,,,, MW-171.
OLMIS-1133 (NR: Can we make a ticket to gather requirements/design/socialize this issue?)
Reference Data
Will be working towards 6.0.1
- This endpoint should filter the facilities (this is a dependency for MW-170)
- (very small)
- (very small)
Stretch:
- (likely shouldn't pick this up, if we did, Reference Data would be working on v7.0.0 - the next major release)
Fulfillment
Platform
- Stretch Goal:
- Stock Management: Change it from Hibernate to Flyway before our next/non-beta release (or move this to Grooming 28?? Team ILL)
Stretch:
Reporting
Roll-over from last sprint.
Issues Discovered During Malawi UAT
Team ILL
- Contract testing dev-wide short presentation (see a few ideas on retrospective)
- 15-minute design meetings after stand-up (do not need a ticket for this; but we will pilot this idea during Sprint 27)
Stretch goals:
- Performance Testing of key endpoints (find the ticket for it)
- Refactor so we can accept the batch approve page in requisitions