Target releaseRelease name or number
EpicReporting - Stock Imbalance
Document status
Priority
eLMIS StatusImplemented
OpenLMIS StatusNot Implemented
PATH 
OpenLMIS Mary Jo Kochendorfer (Deactivated)
JSI Ashraf


Goals/Scope

The stock imbalances report by facility shows lists of facilities that are stocked out, over stocked, under stocked; and to identify products which facilities have left out of the R&R which they should have included.

Status in eLMIS: In eLMIS

Status in OpenLMISNot implemented within OpenLMIS, can be created in Tableau 

Priority: High priority

Background

The stock imbalance report shows lists of facilities and product combinations.

Use:

For each it shows:

Parameters:

Assumptions

User Stories

Short, simple description of a feature told from the perspective of the person who desires the new capability, usually a user or customer of the system.

#TitleUser StoryLabelImportanceNotes
1See under and overstocked levels at facilitiesAs a logistic officer I need to have data on overstocked and understocked facilities so that I can decide on re-distributions of products to ensure they are not out of stock at facilities.Tanzania eLMIS report

Must have


2Identify missing products on R&R for facilitiesAs a logistic officer I need to identify products which facilities have left out of the R&R which they should have included so that products are not out of stock in facilities.Tanzania eLMIS reportMust haveordered quantity on the report
3Export reports to ExcelAs a logistic Officer I need to be able to export all reports and analysis reporting results into Excel so that I can process the data more and analyze it in Excel.Tanzania eLMIS reportsMust have
4Print reports with headings and logsAs a logistic officer I need to be able to print reports with customized headings and logos so that I can file a report for future reference.Tanzania eLMIS reportsMust have

Diagrams

Include any business process mapping, mockups, diagrams or visual designs relating to these requirements. Describes the tasks and the personas who perform those activities. The diagram provides the context for the user stories and serves as a focal point for achieving clarity and agreement among stakeholders. Looks like a standard flow chart.

Dependencies

Identify initial dependencies that are on the critical path for this functionality and may affect the delivery time and serving of business goals. Include links to stories.

DescriptionLink
Name of story or release Link to JIRA


Open Questions

Initial communication between stakeholders and the development team to help understand scope and estimates.

Below is a list of questions to be addressed as a result of this requirements document:

#QuestionOutcomeStatus
1For Tanzania user stories: review the users, "so thats" added, review the label, and review the priority level.Communicate the decision reached Open, In Progress, Closed, and date of closure

Out of Scope