Date

Attendees

Goals

Discussion items

TimeItemWhoNotes

3.5 Release Candidate test plan

  • Risk 1: When to schedule (Starts in Sprint 113)
    • Still in discussion on when to start Release Candidate testing due to Zambia trip (Nov 26-30)
    • Can we start regression testing and Malawi UAT with a smaller subset of team members during that week? Nov 26th
    • Plan release candidate testing for a longer period of time?


  • Status of test plan creation
    • Reorganizing testing to focus on new features first, then regression testing
    • Reviewing test cases created by other teams and adding them to the CoreRegression label OR has this been discussed in Tech Committee?
  • Where do we expect to be with functional testing by the time we start release testing?


Tasks before Release Candidate testing starts:

  • Environments needed
    • Need to let Josh know in advance how many environments we want to set up
    • Who will own each environment? This needs to be listed in the test plan
  • Resources
  • Communication (before we start and during)
  • Exploratory testing & Batch Approval testing
  • Reviewing test cases from JSI before adding them to release candidate testing

Bugs that must be fixed before release candidate

  • Blocker and critical bugs
  • Malawi bugs?

Setting up and managing bug triage

  • Core and Malawi should be included
  • Monitoring Malawi UAT


Sam Im (Deactivated)

Create different test cycles for each team that contain multiple components in each test cycle. 





Action items