Short description

  • total cost of the requisitions is displayed like this

  • total cost is the summation of the priceperpack of requested quantities

    • rounding rules will apply

    • In the authorized and approved state, the Total Cost is the summation of the APPROVED QUANTITIES (PLEASE double check this in 2.0)

  • total cost is dynamic and updates as quantities change

  • user can select to view the break down of the total cost by Full supply and Non-full supply totals

  • Dollar amounts are formatted with Angular's default currency filter ie `amount|currency`

  • when user ships one or more products, then the cost of the skipped procust(s) is omitted from the total cost for the R&R

  • When user unskips one or more skipped products, then the cost of the unskipped products(s) is included in the total cost.



                                                                                                                                                   

Pre – conditions:

                                                                                                                                                                                                                                                       

 

 

Step

Action

Expected system response

Comment

1

                                                                                 Open the requisition and check if Total R&R Cost is displayed properly.                                                                                     

                                                                                                                            

                                                 

2

Check if both cost from Full Supply and Non-Full Supply is are summed in Total R&R Cost.

 

 

3

 Change the Approved Quantity when requisition is authorized. Verify if the Total Requisition Cost is modified.





 

4

 Skip one product.

 The amount of skipped product(s) is omitted from the total cost for R&R.

 

5

 Skip all products.

The amount of skipped product(s) is equals to 0.



 

6

Unskip one/more products

The cost of the unskipped product(s) is included in the total cost.

  • situation when one product is unskipped



 

7

 Add one non-full supply products and check if Total Requisition Cost is changed.

 

 

8

                     Change the requested quantity for non-fully supply product and check if Total Requisition Cost is changed.                     

 

 

 

 