2018-09-10 Ona Reporting Project Plan
Sep 10, 2018
Attendees
@Clay Crosby (Unlicensed)
@Josh Zamor (Deactivated)
@Mary Jo Kochendorfer (Deactivated)
@Wesley Brown
Discussion
Concerns raised about the amount of work to get done in the time left
Some of the work will have to be moved after the 3.5 release
Wes expressed desire to have automated testing included as tickets in this plan
Likely not required for 3.5
VR team will discuss and then discuss with Craig and Clay
Discussed reporting-related travel
Clay to Tanzania
Many people to Kenya for Reporting Building Capacity
Action Items
@Clay Crosby (Unlicensed) Convert spreadsheet to Google sheet and share link
@Clay Crosby (Unlicensed) Update spreadsheet to include information about what is required for 3.5 release
@Clay Crosby (Unlicensed) Reorder line items to match required work order
@Wesley Brown Coordinate agreement with Ona for using demo data
@Josh Zamor (Deactivated) Set up new reporting environment by end of sprint 107 (if you include @Wesley Brown, he can help do this in the future)
@Wesley Brown Set up meeting with @Josh Zamor (Deactivated) and @Mary Jo Kochendorfer (Deactivated) to discuss testing expectations
@Wesley Brown Set up meeting with @Craig Appl (Unlicensed) and @Clay Crosby (Unlicensed) and VR team (TBD) to discuss testing expectations
@Wesley Brown Follow up with @Mary Jo Kochendorfer (Deactivated) to get access to country data or anonymize dataset - a long-term reporting demo data solution is required by Oct 15th
@Wesley Brown Coordinate meeting with Clay in Tanzania the week of Oct 29th
@Wesley Brown Follow up with @Mary Jo Kochendorfer (Deactivated) regarding setting up Report Building Capacity trip to Kenya for the group mentioned during our in-person reporting meeting