2018-09-10 Ona Reporting Project Plan
Attendees
Discussion
- Concerns raised about the amount of work to get done in the time left
- Some of the work will have to be moved after the 3.5 release
- Wes expressed desire to have automated testing included as tickets in this plan
- Likely not required for 3.5
- VR team will discuss and then discuss with Craig and Clay
- Discussed reporting-related travel
- Clay to Tanzania
- Many people to Kenya for Reporting Building Capacity
Action Items
- Clay Crosby (Unlicensed) Convert spreadsheet to Google sheet and share link
- Clay Crosby (Unlicensed) Update spreadsheet to include information about what is required for 3.5 release
- Clay Crosby (Unlicensed) Reorder line items to match required work order
- Wesley Brown Coordinate agreement with Ona for using demo data
- Josh Zamor Set up new reporting environment by end of sprint 107 (if you include Wesley Brown, he can help do this in the future)
- Wesley Brown Set up meeting with Josh Zamor and Mary Jo Kochendorfer (Deactivated) to discuss testing expectations
- Wesley Brown Set up meeting with Craig Appl (Unlicensed) and Clay Crosby (Unlicensed) and VR team (TBD) to discuss testing expectations
- Wesley Brown Follow up with Mary Jo Kochendorfer (Deactivated) to get access to country data or anonymize dataset - a long-term reporting demo data solution is required by Oct 15th
- Wesley Brown Coordinate meeting with Clay in Tanzania the week of Oct 29th
- Wesley Brown Follow up with Mary Jo Kochendorfer (Deactivated) regarding setting up Report Building Capacity trip to Kenya for the group mentioned during our in-person reporting meeting