2018-09-10 Ona Reporting Project Plan

2018-09-10 Ona Reporting Project Plan

Sep 10, 2018 

Attendees

  • Clay Crosby (Unlicensed)

  • Josh Zamor (Deactivated)

  • Mary Jo Kochendorfer (Deactivated)

  • Wesley Brown (Unlicensed)

Discussion

  • Concerns raised about the amount of work to get done in the time left

    • Some of the work will have to be moved after the 3.5 release

  • Wes expressed desire to have automated testing included as tickets in this plan

    • Likely not required for 3.5

    • VR team will discuss and then discuss with Craig and Clay

  • Discussed reporting-related travel

    • Clay to Tanzania

    • Many people to Kenya for Reporting Building Capacity

Action Items

Clay Crosby (Unlicensed) Convert spreadsheet to Google sheet and share link
Clay Crosby (Unlicensed) Update spreadsheet to include information about what is required for 3.5 release
Clay Crosby (Unlicensed) Reorder line items to match required work order
Wesley Brown (Unlicensed) Coordinate agreement with Ona for using demo data
Josh Zamor (Deactivated) Set up new reporting environment by end of sprint 107 (if you include Wesley Brown (Unlicensed), he can help do this in the future)
Wesley Brown (Unlicensed) Set up meeting with Josh Zamor (Deactivated) and Mary Jo Kochendorfer (Deactivated) to discuss testing expectations
Wesley Brown (Unlicensed) Set up meeting with Craig Appl (Unlicensed) and Clay Crosby (Unlicensed) and VR team (TBD) to discuss testing expectations
Wesley Brown (Unlicensed) Follow up with Mary Jo Kochendorfer (Deactivated) to get access to country data or anonymize dataset - a long-term reporting demo data solution is required by Oct 15th
Wesley Brown (Unlicensed) Coordinate meeting with Clay in Tanzania the week of Oct 29th
Wesley Brown (Unlicensed) Follow up with Mary Jo Kochendorfer (Deactivated) regarding setting up Report Building Capacity trip to Kenya for the group mentioned during our in-person reporting meeting