Pick up bugs found during regression testing in this sprint (if time) or as part of next sprint
Mind the Gap:
Not present
Parrot (Sebastian):
Behind on this sprint
Review of regression testing (OLMIS-5225) - waiting on feedback from Josh
Feedback in wiki page looks to be almost complete
If there is more feedback from Josh then we will set up a meeting to go forward
Creating tickets to fill out requisition functional tests epic (
OLMIS-5496: Release Requisition faster with more confidence (basic requisition workflow)Done)
Working with Ben for Angola demo
Ona (Craig):
Updating the ingestion process (OLMIS-side)
OLMIS-5461 (Somewhat blocking)
SSO
OLMIS-5499 (Not blocking)
JSI (Ashraf):
Shipment file work:
Elias Working with Chongsun to answer questions regarding import column settings
OLMIS-5479 and OLMIS-5480 should get done this sprint
OLMIS-5481 and OLMIS-5482 will get some progress but not get completed
OLMIS-5483 and OLMIS-5484 should get done this sprint
Adugna working on quickwins and will take more if finished early