2019-02-08 Team Lead Meeting Notes

Attendees

AshrafClay Crosby (Unlicensed)Craig Appl (Unlicensed)Sebastian BrudzińskiSam Im (Deactivated)Wesley BrownJosh Zamor

Discussion Points

  • Mid-Release Update
    • End of this sprint will mark the mid-way point of the release, should we have the focus of the showcase be on where we're at
    • Sam: MtG may not be ready to showcase anything meaningful/end-user facing yet
    • Sebastian: not too much to showcase other than functional tests progress and performance time improvements
    • Ashraf: JSI could give an update/overview on the shipment file
    • Craig: We could show scoping documents
    • Clay: Janette could show the docs as well
  • Showcase - Keep the 15-minute limit?
    • This is working and we would like to keep it
    • Sebastian: Making sure that each team showcases enough (ie, around 15 minutes) rather than just limited to less than 15
    • Ashraf: We should enforce the showcase stays within 1h
    • Sam: yep, let's stay within 15 minutes per team
  • Wesley Brown Taking off the week after I return to Kenya (Feb 11-15)
    • Will still be checking email and may be available for the showcase on Feb 13
    • Sebastian will lead the meeting next week
  • Reminders:

Mind the Gap (Sam):

  • (behind) Have not started the work plan on the notifications yet because of the focus on multiple suppliers work
    • Hope to get the tickets written before the start of the next sprint
  • Multiple suppliers work is almost done, one ticket carrying over to the next sprint

Parrot (Sebastian):

  • Performance work - get POD requisition work is improved by 5 sec
  • Fixing req for convert is in QA improved from 20 to 10 sec
  • Fixing facility search performance is in progress

Ona (Clay/Craig):

  • Some work on production readiness and prep work for DHIS2 
  • Antonate moving back onto project early next week

JSI (Ashraf):

  • Elias is working on the shipment file - Ashraf: should be done this sprint
  • There's some work on the bugs from requisition
  • Two tickets to scope work for kitting in progress during this sprint
  • Had calls with Nikodem and Sebastian about the reference data seeding tool and the UI for it

Action Items

OpenLMIS: the global initiative for powerful LMIS software