Retrospective

  • This seemed like a typical sprint. The fact that we’re very low on actionable work in the ToDo column that’s directly necessary for the upcoming release poses a risk. The team nevertheless, however, had clear and prioritized work throughout the sprint.

  • The authorization problem we encountered with NiFi stemmed from the fact that NGINX was erroneously routing traffic to port 80 rather than 443.

Showcase

Planning

The development of reports represents the largest body of outstanding work necessary for the first release. We thus reviewed their requirements during this and a dedicated follow-up meeting. The discussion’s content has been incorporated into the page.