Issue Log 

 

CategoryItemWorkaround

Required For:

UAT

Training

Go Live

Post Go Live Fix

Not Required

Fix Date

or Version

Enter DistributionCan't complete distribution after going offline

Stay online

If go offline, keep browser open until all data entered

  
Enter DistributionRemove VAT target groups for all groups besides pregnant mothers from UI   
ReportsAdd Facility Last Visit Date for Delivery Interval Reporting  3/7
Enter Distribution

Distribution that were entered in vrMIS display in SELV (i.e. December 2013). Duplicate data could be entered.

SELV-12 - Getting issue details... STATUS

  

 

Maintenance

If SELV website is updated, firefox users have to clear their cache and manually delete index.db file on their computer before site will work.

Otherwise, there are unexpected errors.

SELV-31 - Getting issue details... STATUS

Use a different browser

Train on manual delete procedure

  
TabletTablet column resizingScroll horizontally  
TabletTablet numeric pop-upSwitch to numeric keypad for each entry  

Release Plan

Plan is for code freeze for initial project scope on 2/28  v.95

Bug fix release 3/14  v1.0

Josh to rebuild following week, and repeat integration testing by 

UAT Entry Criteria Checklist

Key:

GREEN  Already Done

YELLOW  Expect to be completed for UAT starting 3/10

RED  Not expected to be completed for UAT starting 3/10

 

ItemStatusOwner

Estimated Done Date

(90% Confidence)

Notes
  • ThoughtWorks Development Complete (2/28 Scope)
YELLOWRon2/28 
  • ThoughtWork Demos Reviewed/Approved
YELLOWTimoteoDone

Timoteo Chaluco (Unlicensed) validate showcase that will be posted tomorrow by 3PM EAT and send feedback to team

  • Tablet Solution Complete
    • procured
    • connectivity solution
    • lockdown
    • ui changes
    • tested
REDRon3/21

Decide today what tablet to go with & connectivity

Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week

UI changes are outstanding for 3/14, then need to be rolled into build (3/21)

 

  • Data Edit Feature (Access) Complete & Unit Tested
REDRon4/1Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans.
  • VillageReach Analytical Report Workbook Complete & Unit Tested
YELLOWMike2/28 
  • VillageReach Provincial (Portuguese) Workbook Complete & Unit Tested
  • Monthly Summary Report, Map Report, Detail Reports
  • PDF of Monthly Summary Generated (one-off process OK)
  • HSG Feedback Incorporated
  • Calculations Tested
  • In Portuguese
YELLOWMike2/28 
  • SELVdata ETL Complete & Unit Tested
YELLOWJoshJoshAlmost complete. Last Visit Date is only outstanding item
  • vrMIS Data Migration Scripts Complete & Unit Tested
GREENJosh2/27 
  • Architecture Document Complete
GREENJosh1/15 
  • SELV Environment Installed. Procedure Tested & Documented. SSL Cert.
YELLOWJoshJoshJosh talked with Mike and now has access to the service issuing the certificate.  Waiting for their verification process to complete.  No time estimate currently.
  • SELV Reference Data Files Uploaded & System Configured (in Portuguese)
YELLOWJosh2/28 
  • UAT Plan Complete
YELLOWSarah2/28In progress
  • Training Materials Complete (Tablets, Reports, UI)
YELLOWSarah3/7Not started, but confident can be completed before training date
  • Integration End-to-End Tests (SELV-> SELVData -> Reporting)
YELLOWSarah, Vidya, Josh, Timoteo3/7New.
  • Data Completeness Report
REDJoshJOSH to provideNew