UAT Entry Criteria Checklist

 

ItemStatusOwner

Estimated Done Date

(90% Confidence)

Notes
  • ThoughtWorks Development Complete
 Ron  
  • ThoughtWork Demos Reviewed/Approved
 Timoteo  
  • Tablet Solution Complete
    • procured
    • connectivity solution
    • lockdown
    • ui changes
    • tested
 Ron  
  • Data Edit Feature (Access) Complete & Unit Tested
 Ron3/8 
  • VillageReach Analytical Report Workbook Complete & Unit Tested
 Mike Remove from UAT list?
  • VillageReach Provincial (Portuguese) Workbook Complete & Unit Tested
  • Monthly Summary Report, Map Report, Detail Reports
  • PDF of Monthly Summary Generated (one-off process OK)
  • HSG Feedback Incorporated
  • Calculations Tested
  • In Portuguese
 Mike  
  • SELVdata ETL Complete & Unit Tested
 Josh Dependent on TW Dev Complete (+5 days)
  • vrMIS Data Migration Scripts Complete & Unit Tested
 Josh  
  • Architecture Document Complete
GREENJosh1/15 
  • SELV Environment Installed. Procedure Tested & Documented.
 Josh  
  • SELV Reference Data Files Uploaded & System Configured (in Portuguese)
 Josh  
  • SELV Backup/Restore Process Tested & Documented
 Josh  
  • UAT Plan Complete
YELLOWSarah2/28In progress
  • Training Materials Complete
YELLOWSarah3/7Not started, but confident can be completed before training date
  • SELV Pre-Release Testing
REDSarah New. Activity was not planned for. Scope? What is required to validate functionality before launch.
  • Integration End-to-End Tests (SELV-> SELVData -> Reporting)
RED? New. Time not allocated in schedule for this activity. With Mike gone, and SELVData ETL delayed by Thoughtworks, unclear on strategy for integration tests
  • Data Completeness Report
 Josh New
  • Reporting Documentation
   New  Is this needed? What is required?