The Release Candidate Test Plan

...

Mon April 01

Tue April 02

Wed April 03

Thu April 04

Fri April 05

  • Deploy 3.17 RC

  • Start testing

    Testing is focused on regression testing (i.e. manual test case execution) and performance testing. Exploratory and translation testing is performed in the meantime, i.e. during the wait for the bug fixes or when someone doesn’t have any other testing to perform. Exploratory and translation testing has to be done instead of the code freeze tasks.

  • Testing

  • Testing


Week Two:

Mon April 08

  • Testing

Week Three:

Week Four:




Roles & Responsibilities

...

Members

Responsibilities

Questions

Aleksandra Hinc

Artur Lebiedziński

Maciej Grochalski

Krzysztof Pokrywka (Deactivated)

  • Review the list of bugs provided on the QA Slack channel;

    • Only bugs that have been entered and labeled RC1bug will be reviewed during the triage;

  • Prioritize bugs; 

  • Communicate which bugs need to be fixed;

  • Aleksandra Hinc

     to create test cycles for retesting if needed;

  • Aleksandra Hinc

     to provide the status update on the bug fixes on the QA Slack channel as needed;

  • Aleksandra Hinc

     to communicate on Slack the bugs that have been added to the board for the day.

  • When should we meet every day? Meetings will be held every two days (6am PST) and a communication on the bug triage status at the end of the day;

  • Guidance on bug prioritization is located here: http://docs.openlmis.org/en/latest/contribute/contributionGuide.html#reporting-bugs;

  • If there are bugs, then testing for the RC will be done in UAT only;

  • If there are critical/blocker bugs found, then we must retest. If the bugs concern the Reference Data service, all test cases related to the RC in which the bug was found have to be executed again. If the bug concerns any other service, only test cases concerning the service in which it was found have to be executed again;

  • Communication of the test plan before we start testing for the release: