The Release Candidate Test Plan

...

Mon October 21

Tue October 22

Wed October 23

Thu October 24

Fri October 25

  • Deploy 3.18 RC

  • Testing

  • Testing

  • Testing


Week Two:

Mon October 28

Tue October 29

Wed October 30

Thu October 31

Fri November 1

  • Testing

  • Testing

  • Release 3.18 RC

Week Three:

Week Four:




Roles & Responsibilities

...

  • What needs to be communicated daily?

    • The test cycle execution status (including the test cycle's name and % of completion);

    • # of test cases that were executed, passed and failed;

    • Szymon Rujner

       will post any test cases or items that need attention and review by the end of her day on the QA Slack channel;

      Szymon Rujner

       will communicate with the Malawi team (via the Malawi Slack channel) and notify them about the release candidate testing:

      The communication of the scheduled start date before the release candidate testing begins

      ;

    • The communication of when we start the release candidate testing (Malawi has one week to test);

    • The Malawi team is included in the daily bug triage meetings.

  • The best time of day (for each team to communicate the morning status and the end of day status & share blockers): 

    • The beginning of the day: Post what we are doing today;

    • The end of day: Post the status of what we have done, and anything pending.

...