Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

1. Project

...

  • Configuration of Zambezia and Tete provinces
  • Addition of Rotavirus, IPV, and MSD vaccines
  • Usability improvements

2. Scope

The scope of the SELV Updates project includes new configuration for several of the changes, to be completed in advance of the release, as well as new features deployed with the new release in January.

...

Risk
Description

Risk Level

(High, Medium, Low)

Comments
 On-site supportNo onsite training, knowledge transfer, or technical support in Mozambique due to lack of travel budget  MediumAll knowledge transfer and support remote - with minor changes is feasible but risk prolonging issues and miscommunication without on-site support
 Release/deployment dateIdentification of an appropriate date to close access to production for update Medium  
    

5. UAT Plan

List all tasks to be completed for the release including the timeline and responsible individual. Edit existing tasks as applicable to the specific project. 

Validation Testing  
Task
Start
End
Responsible
Status
Comments

Full System Back-up

 

 

Pre-UAT testing

12/28/151/8/16Christine

1st round complete

 

Changes deployed to UAT

 1/8/16

1/14/16Ben

 

 

 

Bring down production system

 

 Functional testing

1/14/161/15/16Christine

 

 

 

Install new version

 

 UAT Testing

1/15/16

1/22/16

Tatenda

 

 

 

Run Upgrade Scripts

 

 Report Testing

1/15/16

1/22/16

Christine

 

 

 

Status Meeting

 

 Bug fixes

1/22/16

1/28/16

Ben

 

 

 

Code Freeze1/28/16 Rich  

 

Status Meeting - Go / No-Go

Training materials complete1/29/16    

6. Deployment Plan

List all deployment tasks with responsible person and timeline. Edit deployment activities as appropriate for the specific project.

   
Activity
Responsible
Timeline
Comments
User AcceptanceTatendaJan. 22nd 
Code FreezeRichJan. 28th 
January Data Entry CompleteTatendaJan. 25th 
SELV Production lockedRich/BenJan. 27th 
Full System Back-up Ben Jan. 29th 
Bring down production system Ben Jan. 29th 
Install new version Ben Jan. 29th 
Run Upgrade Scripts Ben Jan. 29th Status Meeting
Configuration updates Christine Jan. 29th 
Validation Testing  Christine/TatendaJan. 29th 
Status Meeting - Go / No-Go   
    
    
    
    
    
Delivery ChristineJan. 29th 
Training TatendaJan. 29th - ? 
Support ChristineJan. 29 - March 1st