1. Project

A. Overview:

The SELV system deployed in 4 provinces in Mozambique requires several updates and enhancements to improve usability and support scale up to additional provinces. This overall project incorporates several sets of changes including the addition of new vaccines to the system, configuration for two new provinces, and usability enhancements. Additionally, ColdTrace integration with SELV, while development is a separate project (please see linked scope document), will be included in the combined release and deployment plan established for this project.

B. Objectives:

  • Configuration of Zambezia and Tete provinces
  • Addition of Rotavirus, IPV, and MSD vaccines
  • Usability improvements

2. Scope

The scope of the SELV Updates project includes new configuration for several of the changes, to be completed in advance of the release, as well as new features deployed with the new release in January.

In scope:

  • Addition of 3 new vaccines to the SELV system
  • Configuration of system to support rollout in Tete and Zambezia provinces
  • New schedule for North Gaza
  • Updates to Tableau reports to support new vaccine introductions and all items above
  • Upgrade to OpenLMIS 1.0 code
  • Tableau report to track tOPV
  • Updated training materials

A. Release Content

Feature/Change
Description
 OpenLMIS 1.0Upgrade SELV code to the 1.0 version of OpenLMIS 
 ColdTrace Integration Cold Chain Status summary screen for Gaza, Tete, and Niassa (using ColdTrace devices)
Updated Child Coverage screen

 IPV, MSD, and Rotavirus included on the child coverage screen

Change labels to Portuguese names and Portuguese format for ordinal numbers

Stockout days tracking Addition of a column tracking stockout days to the EPI Use screen
Calendar defaultChange the calendar default to the first day of the selected distribution period
HTML tagsAdd HTML tags to all numeric fields to default to a numeric keyboard
Data edit tool updatesUpdate data edit tool to handle all changes in the release

 

3. Production Readiness Criteria

Identify criteria that must be met for release to move to production. Add specific criteria for each category and edit categories as appropriate for the specific project.

Category
Criteria
Responsible
Completed?
Signed off by
Testing
  • Code updated
  • All new features pass functional testing
  • ETL and Tableau functionality confirmed
Christine  
User Acceptance
  • UAT complete
  • Feedback analyzed for necessary changes
Christine  
Training Plan
  • Training schedule created
  • Documentation and support needs identified
Tatenda  
Documentation
  • User manuals and training documentation created/updated
Christine  

4. Risks

Risk
Description

Risk Level

(High, Medium, Low)

Comments
 On-site supportNo onsite training, knowledge transfer, or technical support in Mozambique due to lack of travel budget  MediumAll knowledge transfer and support remote - with minor changes is feasible but risk prolonging issues and miscommunication without on-site support
 Release/deployment dateIdentification of an appropriate date to close access to production for update Medium  
    

5. UAT Plan

Task
Start
End
Responsible
Status
Comments

Pre-UAT testing

12/28/151/8/16Christine

1st round complete

 

Changes deployed to UAT

 1/8/16

1/14/16Ben

 

 

Functional testing

1/14/161/15/16Christine

 

 

UAT Testing

1/15/16

1/22/16

Tatenda

 

 

Report Testing

1/15/16

1/22/16

Christine

 

 

Bug fixes

1/22/16

1/28/16

Ben

 

 

Code Freeze1/28/16 Rich  
Training materials complete1/29/16    

6. Deployment Plan

Activity
Responsible
Timeline
Comments
User AcceptanceTatendaJan. 22nd 
Code FreezeRichJan. 28th 
January Data Entry CompleteTatendaJan. 25th 
SELV Production lockedRich/BenJan. 27th 
Full System Back-upBenJan. 29th 
Bring down production systemBenJan. 29th 
Install new versionBenJan. 29th 
Run Upgrade ScriptsBenJan. 29th 
Configuration updatesChristineJan. 29th 
Validation TestingChristine/TatendaJan. 29th 
Status Meeting - Go / No-GoChristineJan. 29th 
TrainingTatendaJan. 29th - ? 
SupportChristineJan. 29 - March 1st 