Date

 

 https://zoom.us/j/655194422

Attendees

...

...


Goals

  • Review status
  • Highlight or raise any risks
  • Review upcoming travel

...

TimeItemNotes

Check-in on Budget/Spending


  • See the table below
  • Discussion:

Contracting Update

Any concerns or updates?

Double check the contract end dates.

  • Contracts end 31 May 2019
  • Invoiced amounts will decline starting in April

March & April (Sprints 121 &122)  -  Gap Project Review

Team Performance

Please note that performance does NOT include meetings, design work nor testing. Points do not reflect all the work completed but are the best measure at this time and help us understand where the effort is during the sprints.


Team Feedback:

  • Across the board: Wes: The teams have completed their final 3.6 features (or shortly will be) and the testing/release  process will start on MondayOverview
  • Ona
  • JSI (Ashraf)
  • Programming for 3.6 features is complete but testing is ongoing and should be completed by EoB on Friday
  • Working on feedback from reviews
  • MTG (Sam)Will be taking on OLMIS-6152 and complete by tomorrow to include in the 3.6 release

The 3.6 Release


3.6 Feature List

  • Report capacity meeting
  • DHIS2 delivery
  • Kits
  • Shipment File Import
  • Notification Improvements (SMS Notification Channel and Notification Digests)
  • Performance improvements

Do we want to have a retrospective or project review?
  •  Wesley Brown to send out email encouraging team principals to join and/or move the meeting so that can happen
  •  Wesley Brown to discuss the possibility of project retrospective and schedule a meeting if needed

...