Goals

Triage 3.6 bugs

Discussion topics

Sam Im (Deactivated)

Time

Item

Presenter

Notes

Current status

3.6 RC Regression Testing Status:
Phase 2 in progress, so far no Blocker or Critical bugs have been entered. Out of 96 test cases, 32 passed, 7 are in progress, 4 failed and none are blocked so far. 52 remain to be executed.

Reporting testing

In progress


Phase 1 and Phase 2 bugs


No Critical or Blocker bugs have been identified.

Malawi

Environment not deployed yet, and thus testing didn’t start yet

Action items

  •  

Decisions