Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Time

Item

Presenter

Notes

10 min

Status Update

Chongsun Ahn (Unlicensed)

Chongsun:

  • Pipeline is ready

  • eLMIS: casper-elmis.a.openlmis.org

  • v3: casper.a.openlmis.org

Ian:

  • Will try to install Casper stack this week, wasn’t able to do so before

  • Work on UI look more like Tanzania’s

  • Starting to work on the “in-place” upgrade of eLMIS ticket

Question will likely come up about Nifi memory

  • Put some configuration in place in the pipeline to limit Nifi’s memory to 2GB, out of 8GB on the EC2 instance

10 min

Discussion about Casper and Tanzania project as whole

When to demo pipeline?

  • Still in discussion with Ashraf and Elias about details of migration approach

  • Reconvene to demo with Ashraf and Elias and in-country person (GHSC), Alfred Mchau will send out an email to demo the pipeline with folks next week the pipeline, to move things along

  • GHSC person more interest, interested in what magnitude or level of changes post migration

  • Ian to think about how much to keep “look and feel” of UI

Ian:

  • Will try to install Casper stack this week, wasn’t able to do so before

  • Work on UI look more like Tanzania’s

  • Starting to work on the “in-place” upgrade of eLMIS ticket

  • Question will likely come up about Nifi memory

Action items

  •  Alfred Mchau TZ data for testing. Just need a few requisitions, facilities and products to start
  •  Alfred Mchau To provide specifics about what level of polish the mid-July demo needs
  •  Wesley Brown To include Philip in future meetings (timezone withstanding)
  •  Josh Zamor to update location of Philip’s work on deployment
  •  

Decisions

...

  • To send out an email to demo pipeline to Ashraf, Elias, GHSC person, Brandon

Decisions