Monday May 5: Testing & UAT in VillageReach Office

  • AM: Basic set-up and system testing
    • PM: End-to-end UAT with Tatenda

...

Tuesday May 6th: Visit Matola Provincial Office

  • Check SELV functioning on provincial PC
  • Field Coordinator UAT
  • Health Center Visit
  • Test SELV using laptop and on tablet

 

Wednesday May 7th: Visit Xai Xai Provincial Office

  • Check SELV functioning on provincial PC
  • Field Coordinator UAT
  • Test SELV using laptop and on tablet

 

Thursday & Friday, May 8th & 9th: Bug Fixes or Additional Testing in VR Office

  • Bug fixes as necessary
  • Remote testing with Cabo Delgado as possibleUAT
  • Knowledge transfer with Tatenda (as time allows)
  • Review training materials with Tatenda (as time allows)

 

Needs:

  • Letter – Sarah to follow up with Rene
  • Arranging Health Center Visit
  • Tatenda’s time near 100% during visit week – Ruth OKd this

...