- Go to JIRA, then click on Tests, Plan Test Cycle. Select Versions 3.3 2.1 (or whichever release version for this sprint).
- All the test cycles for the sprint will display. There should be at least one for the sprint called "Test Cycle for Sprint XX", there may also be a regression test cycle, and there is the generic Ad hoc test cycle that the system has created.
- Test cases MUST be linked to the Test Cycle so that the execution and metrics are tracked.
- If a test case has been created but not assigned to a test cycle, then you can add them here. Select the test cycle you want to add a test to, then click on the gear button on the right and click "Add Test". Select the tests that need to be added.
...