The projections are high-level projections through the end of the grant. March may have more funding spent around the release time.
Discussion:
Contracting Update
Any concerns or updates?
Double check the contract end dates.
Contracts end 31 May 2019
Invoiced amounts will decline starting in April
For JSI, there are some admin close-out costs in May; hopefully those will be covered by April coming under budget. (May time was not included in the estimate JSI provided.)
Travel Requests
Please submit your USAID concurrence request to Wesley Brown.
Current Plan:
May 6-7 in Nairobi, Kenya, hosted by Ona
Wesley Brown to inform Olivia about this trip, specifically for JSI funding, and confirm that contracts/budgets can support the expected costs and extra time
March & April (Sprints 121 &122) - Gap Project Review
Team Performance
Please note that performance does NOT include meetings, design work nor testing. Points do not reflect all the work completed but are the best measure at this time and help us understand where the effort is during the sprints.
Team Feedback:
Across the board:
Wes: The teams have completed their final 3.6 features (or shortly will be) and the testing/release process will start on Monday
Ona
JSI (Ashraf)
Programming for 3.6 features is complete but testing is ongoing and should be completed by EoB on Friday
Working on feedback from reviews
MTG (Sam)
Will be taking on OLMIS-6152 and complete by tomorrow to include in the 3.6 release