March & April (Sprints 121 &122) - Gap Project Review
Team Performance
Please note that performance does NOT include meetings, design work nor testing. Points do not reflect all the work completed but are the best measure at this time and help us understand where the effort is during the sprints.
Team Feedback:
Overview
Working on the 3.6 release and hoping to be done today or tomorrow on the final issues
Ona (Matt)
Working to get the final release complete. Cleaning up final issues.
JSI (Ashraf)
Features are complete and no Critical or Blocker bugs remain. Just a few minor bugs remain for the future.
Also assisted with the testing for 3.6
MTG
Assisting with testing and bug triage for country testing
Notification Improvements (SMS Notification Channel and Notification Digests)
Performance improvements
Do we want to have a retrospective or project review?
Wesley Brown to send out email encouraging team principals to join and/or move the meeting so that can happen
Wesley Brown to discuss the possibility of project retrospective and schedule a meeting if needed
Do people want to do this?
Brandon: No one is demanding this of us, this is not required. However, it still may be valuable.
Ashraf: Good idea but perhaps a survey may be a good option instead of a meeting. Might be able to get more candid feedback via a survey
Matt: Happy to participate. We have been doing retrospectives throughout the process. Might be easier to meet in person rather than writing things out in a survey
Brandon: Survey might get more participants simply because of timezones
Ashraf: Could also include some indicators that we could pass back to the donor