SELV Deployment Plan
1. Project
A. Overview:
The SELV system deployed in 4 provinces in Mozambique requires several updates and enhancements to improve usability and support scale up to additional provinces. This overall project incorporates several sets of changes including the addition of new vaccines to the system, configuration for two new provinces, and usability enhancements. Additionally, ColdTrace integration with SELV, while development is a separate project (please see linked scope document), will be included in the combined release and deployment plan established for this project.
B. Objectives:
- Configuration of Zambezia and Tete provinces
- Addition of Rotavirus, IPV, and MSD vaccines
- Usability improvements
2. Scope
The scope of the SELV Updates project includes new configuration for several of the changes, to be completed in advance of the release, as well as new features deployed with the new release in January.
In scope:
- Addition of 3 new vaccines to the SELV system
- Configuration of system to support rollout in Tete and Zambezia provinces
- New schedule for North Gaza
- Updates to Tableau reports to support new vaccine introductions and all items above
- Upgrade to OpenLMIS 1.0 code
- Tableau report to track tOPV
- Updated training materials
A. Release Content
Feature/Change | Description |
---|---|
OpenLMIS 1.0 | Upgrade SELV code to the 1.0 version of OpenLMIS |
ColdTrace Integration | Cold Chain Status summary screen for Gaza, Tete, and Niassa (using ColdTrace devices) |
Updated Child Coverage screen | IPV, MSD, and Rotavirus included on the child coverage screen Change labels to Portuguese names and Portuguese format for ordinal numbers |
Stockout days tracking | Addition of a column tracking stockout days to the EPI Use screen |
Calendar default | Change the calendar default to the first day of the selected distribution period |
HTML tags | Add HTML tags to all numeric fields to default to a numeric keyboard |
Data edit tool updates | Update data edit tool to handle all changes in the release |
3. Production Readiness Criteria
Category | Criteria | Responsible | Completed? | Signed off by |
---|---|---|---|---|
Testing |
| Christine |
| Christine |
User Acceptance |
| Christine |
| Christine |
Training Plan |
| Tatenda |
| Tatenda |
Documentation |
| Christine |
|
4. Risks
Risk | Description | Risk Level (High, Medium, Low) | Comments |
---|---|---|---|
On-site support | No onsite training, knowledge transfer, or technical support in Mozambique due to lack of travel budget | Medium | All knowledge transfer and support remote - with minor changes is feasible but risk prolonging issues and miscommunication without on-site support |
Release/deployment date | Identification of an appropriate date to close access to production for update | Medium | |
Initiation of Feb. distributions | The deployment at the beginning of February will likely overlap with some of the distributions in Feb. For the deployment, users will be locked out of the production system and Feb. distributions cannot be initiated ahead of time | Medium | All Feb. distributions that overlap with the deployment should be done on paper. If any Feb. distribution is initiated before the deployment it will be deleted prior to the deployment. |
5. UAT Plan
Task | Start | End | Responsible | Status | Comments |
---|---|---|---|---|---|
Pre-UAT testing | 12/28/15 | 1/8/16 | Christine | Complete |
|
Changes deployed to UAT | 1/8/16 | 1/15/16 | Ben | Complete |
|
Functional testing | 1/14/16 | 1/15/16 | Christine | Complete |
|
Report Testing | 1/15/16 | 1/22/16 | Christine | Complete | |
Bug fixes | 1/15/16 | 1/26/16 | Ben/SolDevelo | Complete | If any bugs in SolDevelo's work are identified at this point, they will be asked to correct them |
Production Release to UAT/Code Freeze | 1/27/16 | 1/27/16 | Ben/Rich | Complete | |
Functional testing | 1/27/16 | 1/29/16 | Christine | Complete | |
Final UAT Testing | 2/1/16 | 2/5/16 | Tatenda | Complete | |
Status Meeting - Go / No-Go | 2/5/16 | 2/5/16 | Christine | Complete |
|
Training materials complete | 1/29/16 | 2/10/16 | Christine/Tatenda | In process |
6. Deployment Plan
Activity | Responsible | Timeline | Comments |
---|---|---|---|
Code Freeze | Rich | Jan. 27th | Pushed to 2/1 for Final Bug Fixes |
User Acceptance | Tatenda | Feb. 5th | |
Status Meeting - Go / No-Go | Christine | Feb. 5th | |
January Data Entry Complete | Tatenda | Feb. 5th | |
SELV Production locked to end users | Rich/Ben | Feb. 8th | |
Full System Back-up | Ben | Feb. 10th | |
Bring down production system | Ben | Feb. 10th | |
Install new version | Ben | Feb. 10th | |
Run Upgrade Scripts | Ben | Feb. 10th | |
Configuration updates | Christine | Feb. 10th | |
Validation Testing | Christine/Tatenda | Feb. 10th | |
Rollback meeting - y/n | Christine | Feb. 12th | |
Training | Tatenda | Jan. 25th - Feb. 12th | Mainly targeted for ColdTrace provinces |
Support | Christine | Feb. 10th - March 1st |