Production "Go Live" Entry Criteria Checklist

Key:

Status
colourGreen
  Already Done

...

Timoteo Chaluco (Unlicensed) validate showcase that will be posted tomorrow by 3PM EAT and send feedback to teamVillageReach Analytical Report Workbook Complete & Unit Tested
ItemStatusOwner

Estimated Done Date

(90% Confidence)

Notes
  •  ThoughtWorks Development Complete (2/28 Scope)
Status
colourGreen
titleDone
Ron2/28 
  •  ThoughtWork Demos Reviewed/Approved
Status
colourYellow
Timoteo 
  •  Tablet Solution Complete
    • procured
    • connectivity solution
    • lockdown
    • ui changes
    • tested
status colourJoshRedRon3/21 

Decide today what tablet to go with & connectivity

Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week

UI changes are outstanding for 3/14, then need to be rolled into build (3/21)

 

  •  Data Edit Feature (Access) Complete & Unit Tested
status 
colourRed
Ron4/1Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans.
  •  
Status
colourYellow
Mike2/28Draft (incomplete) files provided on 2/28. Need to work with Vidya on revised completion date.
  •  VillageReach Provincial (Portuguese) Workbook Complete & Unit Tested
  • Monthly Summary Report, Map Report, Detail Reports
  • PDF of Monthly Summary Generated (one-off process OK)
  • HSG Feedback Incorporated
  • Calculations Tested
  • In Portuguese
Status
colourYellow
Mike2/28Draft (incomplete) files provided on 2/28. Need to work with Vidya on revised completion date.
  •  SELVdata ETL Complete & Unit Tested
Status
colourYellow
JoshJoshAlmost complete. Last Visit Date is only outstanding item
  •  vrMIS Data Migration Scripts Complete & Unit Tested
Status
colourGreen
Josh2/27 
  •  Architecture Document Complete
Status
colourGreen
Josh1/15 
  •  SELV Environment Installed. Procedure Tested & Documented. SSL Cert.
Status
colourYellow
JoshJoshJosh talked with Mike and now has access to the service issuing the certificate.  Waiting for their verification process to complete.  No time estimate currently.
  •  SELV Reference Data Files Uploaded & System Configured (in Portuguese)
Status
colourYellow
Josh2/28 
  •  UAT Plan Complete
Status
colourYellow
Sarah2/28In progress
  •  Training Materials Complete (Tablets, Reports, UI)
Status
colourYellow
Sarah3/7Not started, but confident can be completed before training date
  •  Integration End-to-End Tests (SELV-> SELVData -> Reporting)
Status
colourYellow
Sarah, Vidya, Josh, Timoteo3/7New.
  •  Data Completeness Report
Status
colourRed
JoshJOSH to provideNew
  • PC UAT Plan Executed
 Timoteo  
  •  Tablet UAT Plan Executed
 Timoteo  
  •  Reporting UAT Plan Executed
 Timoteo  
  •  Training Plan & Materials Complete (in Portuguese)
 Sarah  
  •  All critical and blocking bugs resolved (or team agreement to proceed with workarounds)
 Team  
  •  Backup & Restore Tested
 Josh  
  •  Data Completeness Report
 Josh