Production "Go Live" Entry Criteria - Status

Production "Go Live" Entry Criteria - Status

Production "Go Live" Entry Criteria Checklist

Key:

GREEN  Already Done

YELLOW  Expect to be completed for UAT starting 3/10

RED  Not expected to be completed for UAT starting 3/10

 

Item

Status

Owner

Estimated Done Date

(90% Confidence)

Notes

Tablet Solution Complete

 

Josh

 

Decide today what tablet to go with & connectivity

Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week

UI changes are outstanding for 3/14, then need to be rolled into build (3/21)

 

Data Edit Feature (Access) Complete & Unit Tested

 

Ron

4/1

Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans.

PC UAT Plan Executed

 

Timoteo

 

 

Tablet UAT Plan Executed

 

Timoteo

 

 

Reporting UAT Plan Executed

 

Timoteo

 

 

Training Plan & Materials Complete (in Portuguese)

 

Sarah

 

 

All critical and blocking bugs resolved (or team agreement to proceed with workarounds)

 

Team

 

 

Backup & Restore Tested

 

Josh

 

 

Data Completeness Report

 

Josh