UAT Entry Criteria Checklist

Key:

GREEN  Already Done

YELLOW  Expect to be completed for UAT starting 3/10

RED  Not expected to be completed for UAT starting 3/10

 

ItemStatusOwner

Estimated Done Date

(90% Confidence)

Notes
  • ThoughtWorks Development Complete (2/28 Scope)
DONERon2/28 
  • ThoughtWork Demos Reviewed/Approved
YELLOWTimoteo 

Timoteo Chaluco (Unlicensed) validate showcase that will be posted tomorrow by 3PM EAT and send feedback to team

  • Tablet Solution Complete
    • procured
    • connectivity solution
    • lockdown
    • ui changes
    • tested
REDRon3/21

Decide today what tablet to go with & connectivity

Ron and Josh to try the tablet lockdown this week, if not Josh to finish next week

UI changes are outstanding for 3/14, then need to be rolled into build (3/21)

 

  • Data Edit Feature (Access) Complete & Unit Tested
REDRon4/1Ron committing to deliver by 4/1. Sarah to assess how this impacts UAT and training plans.
  • VillageReach Analytical Report Workbook Complete & Unit Tested
YELLOWMike2/28Draft (incomplete) files provided on 2/28. Need to work with Vidya on revised completion date.
  • VillageReach Provincial (Portuguese) Workbook Complete & Unit Tested
  • Monthly Summary Report, Map Report, Detail Reports
  • PDF of Monthly Summary Generated (one-off process OK)
  • HSG Feedback Incorporated
  • Calculations Tested
  • In Portuguese
YELLOWMike2/28Draft (incomplete) files provided on 2/28. Need to work with Vidya on revised completion date.
  • SELVdata ETL Complete & Unit Tested
YELLOWJoshJoshAlmost complete. Last Visit Date is only outstanding item
  • vrMIS Data Migration Scripts Complete & Unit Tested
GREENJosh2/27 
  • Architecture Document Complete
GREENJosh1/15 
  • SELV Environment Installed. Procedure Tested & Documented. SSL Cert.
YELLOWJoshJoshJosh talked with Mike and now has access to the service issuing the certificate.  Waiting for their verification process to complete.  No time estimate currently.
  • SELV Reference Data Files Uploaded & System Configured (in Portuguese)
YELLOWJosh2/28 
  • UAT Plan Complete
YELLOWSarah2/28In progress
  • Training Materials Complete (Tablets, Reports, UI)
YELLOWSarah3/7Not started, but confident can be completed before training date
  • Integration End-to-End Tests (SELV-> SELVData -> Reporting)
YELLOWSarah, Vidya, Josh, Timoteo3/7New.
  • Data Completeness Report
REDJoshJOSH to provideNew