Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Date: Mar 06, 2014

Attendees

Key Notes

  • On-track for UAT Entry Tuesday 3/11

  • Team to assess Production Go Live readiness next week
  • Training & Go-Live date is dependent on:
    • Go live code release date
    • Continual triage of any new bugs identified (new bugs could push date)

Objective

Get team up-to-date on project status and assess readiness to begin UAT on 3/10

Agenda

1. Project Status Update

...

Milestone or ActivitySchedule 2/27Schedule 3/6
Baseline Release2/282/28
UAT-Ready Release3/7 3/10
UAT3/10-3/133/1011-3/28
Go Live Release (Code Freeze)3/7 3/21
Maputo/Gaza Training & Go Live3/144/1: must be +7 days after code freeze
Cabo Delgado/Niassa Training & Go Live3/314/7
Data Edit Tool Complete4/1 4/1

2. UAT Entry Criteria - Status

...

 

Jira Legacy
serverJIRA (openlmis.atlassian.net)
jqlQueryfilter=10300
serverId448ba138-230b-3f91-a83e-16e7db1deed1

 

Action items

    •  @Sarah to review UAT task list with Josh and determine what is needed for Monday

...