Date: Mar 06, 2014
Attendees
Objective
Get team up-to-date on project status and assess readiness to begin UAT on 3/10
Agenda
1. Project Status Update
Completed Last Week |
---|
- ThoughtWorks baseline release complete
- Tablet selected, connectivity solution identified, & tablets purchased
- Initial testing pass completed & bugs triaged (but some more to triage today)
- Tableau workbooks tested and revised
- ThoughtWorks team at work on SELV offline access bug
- Team working in JIRA. Dashboards and releases created, along with significant Wiki content
|
Schedule Updates |
---|
- HSG has decided to do a longer, more thorough UAT period before rolling SELV out to users. Sarah's trip delayed.
- Schedule considerations include:
- When can UAT-Ready Release be completed?
- When can Go Live Release be completed?
|
Milestone or Activity | Schedule 2/27 | Schedule 3/6 |
---|
Baseline Release | 2/28 | 2/28 |
UAT-Ready Release | 3/7 | |
UAT | 3/10-3/13 | 3/10-3/28 |
Go Live Release (Code Freeze) | 3/7 | |
Maputo/Gaza Training & Go Live | 3/14 | 4/1: must be +7 days after code freeze |
Cabo Delgado/Niassa Training & Go Live | 3/31 | 4/7 |
Data Edit Tool Complete | 4/1 | |