2014-03-06 SELV Meeting Agenda
Date: Mar 06, 2014
Attendees
Key Notes
On-track for UAT Entry Tuesday 3/11
- Team to assess Production Go Live readiness next week
- Training & Go-Live date is dependent on:
- Go live code release date
- Continual triage of any new bugs identified (new bugs could push date)
Objective
Get team up-to-date on project status and assess readiness to begin UAT on 3/10
Agenda
1. Project Status Update
Completed Last Week |
---|
|
Schedule Updates |
---|
|
Milestone or Activity | Schedule 2/27 | Schedule 3/6 |
---|---|---|
Baseline Release | 2/28 | 2/28 |
UAT-Ready Release | 3/7 | 3/10 |
UAT | 3/10-3/13 | 3/11-3/28 |
Go Live Release (Code Freeze) | 3/7 | 3/21 |
Maputo/Gaza Training & Go Live | 3/14 | 4/1: must be +7 days after code freeze |
Cabo Delgado/Niassa Training & Go Live | 3/31 | 4/7 |
Data Edit Tool Complete | 4/1 | 4/1 |
2. UAT Entry Criteria - Status
3. Bug Triage
Action items
- @Sarah to review UAT task list with Josh and determine what is needed for Monday