Note | ||
---|---|---|
| ||
This test plan is being updated to support release candidate testing in Sprint 113. |
...
- Please execute the test cases in the order that they are listed in the test cycle, as assigned to you by the QA lead
- If no Blocker or Critical bugs, then move to the release candidate deployment and testing
- RC Phase 1&2 (Two full days of testing for all teams, and 2 days for bug fixes and bug fix testing) for each release candidate as needed
- Testing will be done in test and uat environments (Sam Im (Deactivated) add links to new environments here)
- Team Fast Parrot environment: TBD: https://uat3.openlmis.org
- Team JSI environment: TBD https://uat4.openlmis.org
- Team Mind the Gap environment: TBD https://uat.openlmis.org
- Team Ona environment: TBD:https://uat4.openlmis.org
- Performance testing (data set and environment set up)
- How to enter bugs:Testing Process & Test Plans#EnterDefectsduringsprinttesting
- Prioritization of bugs:http://docs.openlmis.org/en/latest/contribute/contributionGuide.html#reporting-bugs
Test Phase | Components/Features | Assigned in Test Cycle | Dates | QA lead responsibilities |
---|---|---|---|---|
Phase 1 | New features for 3.5 release Reporting: https://docs.google.com/document/d/1pVlgGXV9nb-nYlrTCRHS7Sor8ZrcnL59ch_Lnn2whZ0/edit | New features test cases will have 3.5 fix version (Joanna Bebak (Deactivated) Joanna Szymańska (Deactivated) to update) | 1 full day each team | Team Fast Parrot:
Team Mind the Gap: Sam Im (Deactivated)
Team JSI: Team Ona Gap: |
Bug triage | Bug triage for Phase 1 | Phase 1 Bug test cycle | 1 full day This bug test cycle is done in parallel (on the same day - as Phase 2 below) | |
Phase 2 | Regression Exploratory Testing Translations Performance Testing | 3.5 RC2 | 1 full day each team |
|
Bug triage | Bug triage for Phase 2 | Phase 2 Bug test cycle | 1 full day (as needed) |
...