titleTest Plan Work in Progress

This test plan is being updated to support release candidate testing in Sprint 113.

...


Test Phase
Components/Features
Assigned in Test Cycle
Dates
QA lead responsibilities
Phase 1

New features for 3.5 release

Reporting: https://docs.google.com/document/d/1pVlgGXV9nb-nYlrTCRHS7Sor8ZrcnL59ch_Lnn2whZ0/edit

New features test cases will have 3.5 fix version (Joanna Bebak (Deactivated) Joanna Szymańska (Deactivated) to update)




1 full day each team

Team Fast Parrot: 

  • Joanna will provide status of testing by end of day. 
  • Joanna will triage and prioritize any bugs found in Phase 1
  • If there are Blocker or Critical bugs they will be assigned to a 3.5Phase1Bug test cycle 
  • Bugs are labeled 3.5Phase1bug

Team Mind the Gap: Sam Im (Deactivated)

  • Sam will provide status of testing by end of day.
  • Sam will triage and prioritize any bugs found in Phase 1

Team JSI: 

Team Ona Gap: 

Bug triageBug triage for Phase 1

Phase 1 Bug test cycle

1 full day 

This bug test cycle is done in parallel (on the same day -  as Phase 2 below)


Phase 2

Regression

Exploratory Testing

Translations

Performance Testing

3.5 RC2




1 full day each team

  • Anyone not participating in bug fixes will complete Edge case, exploratory or translation testing
  • For all bug fixes, we will require pre-push reviews via pull requests or have more reviewers for any change. If reviews are still pending at the end of the day, please mention the reviewer in slack.
  • Mateusz Kwiatkowski will lead performance testing
  • Bugs are labeled 3.5Phase2bug
Bug triageBug triage for Phase 2Phase 2 Bug test cycle1 full day  (as needed)


...