Sam Im (Deactivated) and Joanna Bebak (Deactivated) to review 3.3 plan and create a 3.4 test plan here.

...


Test Phase
Components/Features
Assigned in Test Cycle
Dates
QA lead responsibilities
Phase 1

Requisitions (Team JSI)

Fulfillment (Team Parrot)

Stock Management (Team Parrot)

CCE (Team Mind the Gap)

Administration/Reference-data UI (Team Mind the Gap)

Reporting (Team Ona Gap)

Team Mind the Gap: 3.4 Administration (Reference Data) RC1

3.4 CCE RC1



Reporting: Testing the OpenLMIS Reporting Stack

1 full day each team

Team Parrot: 

  • Joanna will provide status of testing by end of day. 
  • Joanna will triage and prioritize any bugs found in Phase 1
  • If there are Blocker or Critical bugs they will be assigned to a 3.4Phase 1 Bug test cycle 
  • Bugs are labeled 3.4Phase1bug

Team Mind the Gap: Sam Im (Deactivated)

  • Sam will provide status of testing by end of day.
  • Sam will triage and prioritize any bugs found in Phase 1

Team JSI: Testing Requisitions

Team Ona Gap: Testing Reporting

Bug triageBug triage for Phase 1

Phase 1 Bug test cycle

1 full day 

This bug test cycle is done in parallel (on the same day -  as Phase 2 below)


Phase 2

Bug Fixes & edge cases

Exploratory Testing

Translations

Performance Testing for:

  • Regression
  • New features

3.4 RC2

Team Mind the Gap: 3.4 ReferenceData RC2

3.4 CCE RC2




1 full day each team

  • Anyone not participating in bug fixes will complete Edge case, exploratory or translation testing
  • For all bug fixes, we will require re-push reviews via pull requests or have more reviewers for any change. If reviews are still pending at the end of the day, please mention the reviewer in slack.
  • Brandon and one other team member will complete performance testing
  • Bugs are labeled 3.4Phase2bug
Bug triageBug triage for Phase 2Phase 2 Bug test cycle1 full day  (as needed)


...