Sam Im (Deactivated) and Joanna Bebak (Deactivated) to review 3.3 plan and create a 3.4 test plan here.
...
Test Phase | Components/Features | Assigned in Test Cycle | Dates | QA lead responsibilities |
---|---|---|---|---|
Phase 1 | Requisitions (Team JSI) Fulfillment (Team Parrot) Stock Management (Team Parrot) CCE (Team Mind the Gap) Administration/Reference-data UI (Team Mind the Gap) Reporting (Team Ona Gap) | Team Mind the Gap: 3.4 Administration (Reference Data) RC1 Reporting: Testing the OpenLMIS Reporting Stack | 1 full day each team | Team Parrot:
Team Mind the Gap: Sam Im (Deactivated)
Team JSI: Testing Requisitions Team Ona Gap: Testing Reporting |
Bug triage | Bug triage for Phase 1 | Phase 1 Bug test cycle | 1 full day This bug test cycle is done in parallel (on the same day - as Phase 2 below) | |
Phase 2 | Bug Fixes & edge cases Exploratory Testing Translations Performance Testing for:
| 3.4 RC2 Team Mind the Gap: 3.4 ReferenceData RC2 | 1 full day each team |
|
Bug triage | Bug triage for Phase 2 | Phase 2 Bug test cycle | 1 full day (as needed) |
...