Item | Time | Lead |
---|
Review status of the roadmap and development progress. - testing environment will be up by the end of Sprint 8 (September 20)
- Sprint 7 finishes this week. Key items to be completed:
- v2/v3 Requisition Assessment
- Reference data pulled out as its own service
- RBAC implemented
- New product model implemented
- UI configured, UI working for login
- Upcoming sprint will focus on:
- Stitching the UI together with requisitions
- Continue on Requisition template
- Continue on Export to Order and UI.
- Showcase Information is located here, under Project Management
| 15 min | |
Audit logging approach and scope - Types: Updates vs. Activities
- Scope: All vs. Select
- Strategy / Tool
| 20 min | |
New logo and branding effort | 5 min | |
New opportunities and projects | 10 min | |
TBD |
|
|
Risks: - Risk #7. OpenLMIS community stays dependent on centralized funding from 1-2 primary sources and fails to diversify and encompass open source development principles
- Risk #6. OpenLMIS community fails to grow. Stays small and driven by self-interest
- Risk #5. Perception of code review as an acceptance of the story. The role of code review.
- New risk identified by Lakshmi: Countries do not migrate to 3.0.
| 10 min | |