Test Case #:1451
| Test Case Name: View the Total Requisition Cost
|
System: openLMIS
| Subsystem: blue |
Test case designed by: Lucyna Laska | Design Date:17.01.2017 |
Short description: - total cost of the requisitions is displayed like this
- total cost is the summation of the priceperpack of requested quantities
- rounding rules will apply
- In the authorized and approved state, the Total Cost is the summation of the APPROVED QUANTITIES (PLEASE double check this in 2.0)
- total cost is dynamic and updates as quantities change
- user can select to view the break down of the total cost by Full supply and Non-full supply totals
- Dollar amounts are formatted with Angular's default currency filter ie `amount|currency`
- when user ships one or more products, then the cost of the skipped procust(s) is omitted from the total cost for the R&R
- When user unskips one or more skipped products, then the cost of the unskipped products(s) is included in the total cost.
| |
Step | Action | Expected system response | Comment |
1 | Open the requisition and check if Total R&R Cost is displayed properly. | | |
2 | Check if both cost from Full Supply and Non-Full Supply is are summed in Total R&R Cost. | | |
3 | Change the Approved Quantity when requisition is authorized. Verify if the Total Requisition Cost is modified. | | |
4 | | The amount of skipped product(s) is omitted from the total cost for R&R.
| |
5 | Skip all products. | The amount of skipped product(s) is equals to 0.
| |
6 | Unskip one/more products | The cost of the unskipped product(s) is included in the total cost.
| |
7 | | | |
8 | | | |