Objective

  • Review project status
  • Assess readiness to begin UAT on 3/10
  • Bug Triage

Agenda

  1. Project Status Update
    1. Completed Last Week
      • ThoughtWorks baseline stories complete
      • Tablet selected, connectivity solution identified, & tablets purchased
      • Initial testing pass completed & bugs triaged (but some more to triage today)
      • Tableau workbooks tested and revised
      • ThoughtWorks team at work on SELV offline access bug
      • Team working in JIRA. Dashboards and releases created, along with significant Wiki content

    2. Schedule Updates
      1. HSG has decided to do a longer, more thorough UAT period before rolling SELV out to users. Sarah's trip delayed.
      2. Schedule considerations include:
        1. When can UAT-Ready Release be completed?
        2. When can Go Live Release be completed?

 

Milestone or ActivitySchedule 2/27Schedule 3/6
Baseline Release2/282/28
UAT-Ready Release3/7 
UAT3/10-3/133/10-3/28
Go Live Release (Code Freeze)3/7 
Maputo/Gaza Training & Go Live3/144/1: must be +7 days after code freeze
Cabo Delgado/Niassa Training & Go Live3/314/7
Data Edit Tool Complete4/1 

 

 