Date
Mar 05, 2014
Attendees
Objective
- Review project status
- Assess readiness to begin UAT on 3/10
- Bug Triage
Agenda
- Project Status Update
- Completed Last Week
- ThoughtWorks baseline stories complete
- Tablet selected, connectivity solution identified, & tablets purchased
- Initial testing pass completed & bugs triaged (but some more to triage today)
- Tableau workbooks tested and revised
- ThoughtWorks team at work on SELV offline access bug
- Team working in JIRA. Dashboards and releases created, along with significant Wiki content
- Schedule Updates
- HSG has decided to do a longer, more thorough UAT period before rolling SELV out to users. Sarah's trip delayed.
- Schedule considerations include:
- When can UAT-Ready Release be completed?
- When can Go Live Release be completed?
- Completed Last Week
Milestone or Activity | Schedule 2/27 | Schedule 3/6 |
---|---|---|
Baseline Release | 2/28 | 2/28 |
UAT-Ready Release | 3/7 | |
UAT | 3/10-3/13 | 3/10-3/28 |
Go Live Release (Code Freeze) | 3/7 | |
Maputo/Gaza Training & Go Live | 3/14 | 4/1: must be +7 days after code freeze |
Cabo Delgado/Niassa Training & Go Live | 3/31 | 4/7 |
Data Edit Tool Complete | 4/1 |
2. UAT Entry Criteria - Status
3. Bug Triage
3.
Action items