Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 2 Next »

Date: Mar 06, 2014

Attendees

Objective

Get team up-to-date on project status and assess readiness to begin UAT on 3/10

Agenda

1. Project Status Update

 

 Completed Last Week

    • ThoughtWorks baseline stories complete
    • Tablet selected, connectivity solution identified, & tablets purchased
    • Initial testing pass completed & bugs triaged (but some more to triage today)
    • Tableau workbooks tested and revised
    • ThoughtWorks team at work on SELV offline access bug
    • Team working in JIRA. Dashboards and releases created, along with significant Wiki content
 
 Schedule Updates
    • HSG has decided to do a longer, more thorough UAT period before rolling SELV out to users. Sarah's trip delayed.
    • Schedule considerations include:
        • When can UAT-Ready Release be completed?
        • When can Go Live Release be completed?
 
Milestone or ActivitySchedule 2/27Schedule 3/6
Baseline Release2/282/28
UAT-Ready Release3/7 
UAT3/10-3/133/10-3/28
Go Live Release (Code Freeze)3/7 
Maputo/Gaza Training & Go Live3/144/1: must be +7 days after code freeze
Cabo Delgado/Niassa Training & Go Live3/314/7
Data Edit Tool Complete4/1 

2. UAT Entry Criteria - Status

3. Bug Triage

 

type key summary assignee reporter priority status resolution created updated due
Loading...
Refresh

 

Action items

    •  
  • No labels